Planned, Expected and Actual: Difference between revisions

From ReliaWiki
Jump to navigation Jump to search
mNo edit summary
Line 35: Line 35:


If we define Action 1 to start on May 1 and run for 10 days, and Action 2 to start after Action 1 is completed and also run for 10 days then our plan would be as follows:  
If we define Action 1 to start on May 1 and run for 10 days, and Action 2 to start after Action 1 is completed and also run for 10 days then our plan would be as follows:  




{| class="wikitable" <!-- generated with [[w:de:Wikipedia:Technik/Text/Basic/EXCEL-Tabellenumwandlung]] V2.0 -->
{| class="wikitable" <!-- generated with [[w:de:Wikipedia:Technik/Text/Basic/EXCEL-Tabellenumwandlung]] V2.0 -->
|- style="font-weight:bold" align="center"
|- align="center"
|style="background-color:#EAEAEA" width="48" height="51" | Name
|style="background-color:#EAEAEA" align="right" width="109" height="26" | &nbsp;
|style="background-color:#EBF1DE" width="48" | Start Date
|style="background-color:#EBF1DE" width="80" | Planned Start Date
"|style=""background-color:#EBF1DE"" width=""48"" | Duration
"|style=""background-color:#EBF1DE"" width=""87"" | Duration
<br />(Business Days)"
<br />(Business Days)"
|style="background-color:#EBF1DE" width="48" | Due Date
|style="background-color:#EBF1DE" width="61" | Planned Due Date
|style="background-color:#B7DEE8" width="48" | Feasible Start Date
|style="background-color:#B7DEE8" width="76" | Feasible Start Date
|style="background-color:#B7DEE8" width="48" | Feasible Duration
|style="background-color:#B7DEE8" width="70" | Feasible Duration
|style="background-color:#B7DEE8" width="48" | Feasible Due date
|style="background-color:#B7DEE8" width="65" | Feasible Due date
|style="background-color:#FABF8F" width="48" | Actual Start Date
|style="background-color:#FABF8F" width="67" | Actual Start Date
|style="background-color:#FABF8F" width="48" | Actual Duration
|style="background-color:#FABF8F" width="69" | Actual Duration
|style="background-color:#FABF8F" width="48" | Completion Date
|style="background-color:#FABF8F" width="82" | Actual Completion Date


|- style="background-color:#808080;color:#FFFFFF"
|- style="font-weight:bold"
| height="15" valign="top" | Project
| height="15" valign="top" | Project
| align="center" valign="top" | 5/1/2020
| align="center" valign="top" | May-20
| align="right" align="center" valign="top" | 20
| align="right" align="center" valign="top" | 20
| align="center" valign="top" | 5/20/2020
| align="center" valign="top" | May-20
| align="center" valign="top" | 5/1/2020
| align="center" valign="top" | May-20
| align="right" align="center" valign="top" | 20
| align="right" align="center" valign="top" | 20
| align="center" valign="top" | 5/20/2020
| align="center" valign="top" | May-20
| align="center" valign="top" | ?
| align="center" valign="top" | ?
| align="center" valign="top" | ?
| align="center" valign="top" | ?
| align="center" valign="top" | ?
| align="center" valign="top" | ?


|-  
|- style="background-color:#FDE9D9"
| height="26" valign="top" |       Gate A
| height="15" valign="top" | ----> Gate A
| align="center" valign="top" | 5/1/2020
| align="center" valign="top" | May-20
| align="right" align="center" valign="top" | 10
| align="right" align="center" valign="top" | 10
| align="center" valign="top" | 5/10/2020
| align="center" valign="top" | May-20
| align="center" valign="top" | 5/1/2020
| align="center" valign="top" | May-20
| align="right" align="center" valign="top" | 10
| align="right" align="center" valign="top" | 10
| align="center" valign="top" | 5/10/2020
| align="center" valign="top" | May-20
| align="center" valign="top" | ?
| align="center" valign="top" | ?
| align="center" valign="top" | ?
| align="center" valign="top" | ?
Line 76: Line 78:


|-  
|-  
| height="26" valign="top" |             Action 1
| height="15" valign="top" | --------->Action 1
| align="center" valign="top" | 5/1/2020
| align="center" valign="top" | May-20
| align="right" align="center" valign="top" | 10
| align="right" align="center" valign="top" | 10
| align="center" valign="top" | 5/10/2020
| align="center" valign="top" | May-20
| align="center" valign="top" | 5/1/2020
| align="center" valign="top" | May-20
| align="right" align="center" valign="top" | 10
| align="right" align="center" valign="top" | 10
| align="center" valign="top" | 5/10/2020
| align="center" valign="top" | May-20
| align="center" valign="top" | ?
| align="center" valign="top" | ?
| align="center" valign="top" | ?
| align="center" valign="top" | ?
| align="center" valign="top" | ?
| align="center" valign="top" | ?


|-  
|- style="background-color:#FDE9D9"
| height="26" valign="top" |       Gate B
| height="15" valign="top" | ---->Gate B
| align="center" valign="top" | 5/11/2020
| align="center" valign="top" | May-20
| align="right" align="center" valign="top" | 10
| align="right" align="center" valign="top" | 10
| align="center" valign="top" | 5/20/2020
| align="center" valign="top" | May-20
| align="center" valign="top" | 5/11/2020
| align="center" valign="top" | May-20
| align="right" align="center" valign="top" | 10
| align="right" align="center" valign="top" | 10
| align="center" valign="top" | 5/20/2020
| align="center" valign="top" | May-20
| align="center" valign="top" | ?
| align="center" valign="top" | ?
| align="center" valign="top" | ?
| align="center" valign="top" | ?
Line 100: Line 102:


|-  
|-  
| height="26" valign="top" |             Action 2
| height="15" valign="top" | --------->Action 2
| align="center" valign="top" | 5/11/2020
| align="center" valign="top" | May-20
| align="right" align="center" valign="top" | 10
| align="right" align="center" valign="top" | 10
| align="center" valign="top" | 5/20/2020
| align="center" valign="top" | May-20
| align="center" valign="top" | 5/11/2020
| align="center" valign="top" | May-20
| align="right" align="center" valign="top" | 10
| align="right" align="center" valign="top" | 10
| align="center" valign="top" | 5/20/2020
| align="center" valign="top" | May-20
| align="center" valign="top" | ?
| align="center" valign="top" | ?
| align="center" valign="top" | ?
| align="center" valign="top" | ?
Line 112: Line 114:


|}
|}


<br>  
<br>  

Revision as of 12:21, 24 July 2014

This is a subpage of a larger section.
Return to: DFR Planner





Planned, Feasible and Actual

  • Planned dates and data hold the original dates and data (start end, duration, cost etc.) put in the planner.
  • Actual dates and data hold the final actual dates and data as recorded by the team on task/action/gate start/completion.
  • Feasible dates and data are automatically and continuously updated based on how the project progresses.
    • Feasible Start Date is the earliest possible date the gate or action can start (based on prior dependencies). If there is no precedence or dependencies this is equal to the planned start date.
    • Feasible End Date is the expected completion date.
    • Feasible Duration is the length (in days) of the available time window to complete the action/gate.

In the ideal scenario, where each item is completed on-time and exactly as planned, all three are the same. In the real world however this is rarely the case.

As an example consider the following scenario:

  • Assume a project has two gates, A and B, and gate B has A as a precedence.
  • Each gate has one action item below it namely Action 1 and 2 respectively.
  • Assume 7 day work weeks and no holidays.


Then, the hierarchy would be as follows:

  • Project
  • Gate A
Action 1
  • Gate B
Action 2
Initial Planning

If we define Action 1 to start on May 1 and run for 10 days, and Action 2 to start after Action 1 is completed and also run for 10 days then our plan would be as follows:



  Planned Start Date

"|style=""background-color:#EBF1DE"" width=""87"" | Duration
(Business Days)"

Planned Due Date Feasible Start Date Feasible Duration Feasible Due date Actual Start Date Actual Duration Actual Completion Date
Project May-20 20 May-20 May-20 20 May-20 ? ? ?
----> Gate A May-20 10 May-20 May-20 10 May-20 ? ? ?
--------->Action 1 May-20 10 May-20 May-20 10 May-20 ? ? ?
---->Gate B May-20 10 May-20 May-20 10 May-20 ? ? ?
--------->Action 2 May-20 10 May-20 May-20 10 May-20 ? ? ?




Project Planned Feasible Actual
Start Duration End Start Duration End Start Duration End
May 1 20 May 20 May 1 20 May 20  ?  ?  ?
Gate A Planned Feasible Actual
Start Duration End Start Duration End Start Duration End
May 1 10 May 10 May 1 10 May 10  ?  ?  ?


Action 1 Planned Feasible Actual
Start Duration End Start Duration End Start Duration End
May 1 10 May 10 May 1 10 May 10  ?  ?  ?


Gate B Planned Feasible Actual
Start Duration End Start Duration End Start Duration End
May 11 10 May 20 May 11 10 May 20  ?  ?  ?


Action 2 Planned Feasible Actual
Start Duration End Start Duration End Start Duration End
May 11 10 May 20 May 11 10 May 20  ?  ?  ?



Not that at this point, Planned and feasible are identical.

After the Start of Action 1

Now assume that Action 1 was started on May 3 instead of May 1 as planned. Then the plan would automatically be shifted as follows:


Project Planned Feasible Actual
Start Duration End Start Duration End Start Duration End
May 1 20 May 21 May 1 23 May 23  May 3  ?  ?
Gate A Planned Feasible Actual
Start Duration End Start Duration End Start Duration End
May 1 10 May 11 May 1 13 May 13  May 3  ?  ?


Action 1 Planned Feasible Actual
Start Duration End Start Duration End Start Duration End
May 1 10 May 11 May 1 13 May 13  May 3  ?  ?


Gate B Planned Feasible Actual
Start Duration End Start Duration End Start Duration End
May 11 10 May 21 May 13 10 May 23  ?  ?  ?


Action 2 Planned Feasible Actual
Start Duration End Start Duration End Start Duration End
May 11 10 May 21 May 13 10 May 23  ?  ?  ?




Specifically the late start of Action 1 would push the feasible end date of Action 1 forward and automatically cause other related dates to shift (in orange). 

After the Completion of Action 1

Now assume that Action 1 was completed on May 12 (a day earlier than feasible. Then the plan would automatically be shifted as follows:


Project Planned Feasible Actual
Start Duration End Start Duration End Start Duration End
May 1 20 May 21 May 1 22 May 22  May 3  ?  ?
Gate A Planned Feasible Actual
Start Duration End Start Duration End Start Duration End
May 1 10 May 11 May 1 13 May 13  May 3 9 May 12


Action 1 Planned Feasible Actual
Start Duration End Start Duration End Start Duration End
May 1 10 May 11 May 1 13 May 13  May 3   9   May 12


Gate B Planned Feasible Actual
Start Duration End Start Duration End Start Duration End
May 11 10 May 21 May 12 10 May 22  ?  ?  ?


Action 2 Planned Feasible Actual
Start Duration End Start Duration End Start Duration End
May 11 10 May 21 May 12 10 May 22  ?  ?  ?






Return to the parent page DFR Planner

End Section

SynXBuild.gif


Basis, Impact & Discussion

Basis for Modification

Basis Discuss

Impact on V8/V9 Users

Impact Discuss

Discussion Comment on this feature, or discuss it in the Synthesis Discussion area of our Discussion Forums.

These pages are not intended to replace, or be used in-lieu of the official software documentation. They are working/developments notes intended to facilitate communication between the user community and the development team. Features and specifications listed here are for discussion purposes and their final implementation in may be different than the specifications presented here.